IMG_0106.jpg
Aug. 16: Another view of the lobby from the new restroom.
|
IMG_0129.jpg
Aug 30: The lower-level landing for the lift, as seen from the bottom of the stairs. The lounge is to the far left. The opening in the back wall is the bottom of the ground-level entrance to the lift.
|
IMG_0107.jpg
Aug 16: The future home of the costume closet, under the new restroom.
|
IMG_0123.jpg
Aug 24: They've graded the dirt around the foundation, but otherwise there's not much change outside. All the work is going on inside.
|
IMG_0115.jpg
Aug 24: The inside wall of the new restroom. They've started on the electrical work, and they're cutting a trough for the plumbing. The wall you see is the old exterior wall of the auditorium; it will be covered with sheetrock.
|
IMG_0121.jpg
Aug 24: The other side wall of the restroom. The electrical lines have been run. The opening behind the 2x4s is the lift shaft.
|